Gridcog for data centres
Data centre power modelling: grid connections, storage and onsite generation
A data centre can get power years sooner by accepting a flexible grid connection, whether timed, phased or curtailed in real time, and covering the gap with battery storage, onsite generation or flexible compute. Gridcog models the connection, the load and every onsite asset together, so developers can size each option and see what it costs before investing.
Key points
125 GW
In Great Britain, demand connection applications grew from 41 GW to 125 GW in under a year, with data centre projects accounting for at least 80 GW (Ofgem, 29 July 2026).
5–7 years
Grid connections can take five to seven years, against plans to bring new data centres online within two (encoord, December 2025).
Ireland
In Ireland, larger data centres must bring dispatchable generation or storage matching their maximum import capacity to connect (CRU, 16 December 2025).
£795m
In Gridcog modelling of a 100 MW data centre in Slough, a microgrid portfolio with a smaller connection cut 15-year cost from about £1.9bn on full grid supply to £795m.
How can a data centre get power sooner?
By connecting on flexible terms instead of waiting for a firm connection.
A firm connection obliges the network operator to build whatever reinforcement full capacity needs, and that reinforcement causes most of the delay. A flexible connection removes the guarantee for some hours or conditions, so the site connects earlier and usually pays less.
Four ways to connect sooner
Option 01 of 04
Timed or scheduled
Import capped in agreed hours, days or seasons
Grid import allowedIllustrative, not to scale
Notice before reduction
Known in advance
Best fit
Workloads that can be shifted or batched
Option 02 of 04
Flexible now, firm later
Restricted import until reinforcement is done, then firm
Grid import allowedIllustrative, not to scale
Notice before reduction
Known; capacity steps up
Best fit
Space let to tenants on a firm service level
Option 03 of 04
Real-time curtailment (active network management)
Automated control reduces import when the network nears its limit
Grid import allowedIllustrative, not to scale
Notice before reduction
Limited; two minutes to acknowledge in Ireland
Best fit
Sites with significant onsite generation already committed
Option 04 of 04
Bring your own generation
Onsite storage or generation picks up the load when grid supply drops
Grid import allowedOnsite storage or generationIllustrative, not to scale
Notice before reduction
Covers any of the above
Best fit
Mandatory for larger sites in Ireland
Backup generation and batteries are already part of most data centre designs for resilience, and the same equipment can ride through a curtailment event. The real cost is any extra generation or storage needed so compute never drops, plus the fuel and cycling to run it. That cost rises as notice falls.
How do you model a flexible connection before investing?
Apply the connection as a Site Import Schedule, then autosize storage or generation against it and compare scenarios.
Gridcog Energy Analyst Joshua Elliott did this for a 100 MW data centre on an example winter peak timed connection.

Joshua Elliott
Energy Analyst
- 1
Connection only
What changes
Winter peak import limit, no supporting generation
Result
Periods of unserved load during evening peaks
- 2
Autosized standalone battery
What changes
Battery charges at midday within the import limit and discharges at the winter peaks
Result
Unserved load removed; peak-time network costs avoided
- 3
Autosized battery and solar
What changes
Battery discharges in the same intervals, partly from solar
Result
Lower grid import costs again
Timed and phased limits are set in the schedule editor; real-time curtailment is uploaded as interval data so its randomness is reflected.
Read flexible grid connections for data centres: GB and Ireland→Want to test your site's connection options?
Model your project in Gridcog →What does a data centre's power strategy cost over its life?
It depends far more on the mix of grid, onsite generation and storage than on any one asset.
In Gridcog modelling of a hypothetical 100 MW data centre in Slough:
A microgrid portfolio with a smaller connection cut 15-year cost from about £1.9bn to £795m
15-year cost by power strategy, hypothetical 100 MW data centre in Slough (£)
| Power strategy | 15-year cost |
|---|---|
| Full grid supply | About £1.9bn |
| Part of the connection swapped for a 50 MW gas genset | About £1.79bn |
| Microgrid portfolio of solar, wind and storage with a smaller connection | About £795m |
Full grid supply
About £1.9bn
Part of the connection swapped for a 50 MW gas genset
About £1.79bn
Microgrid portfolio of solar, wind and storage with a smaller connection
About £795m
Should a data centre use a genset or a fuel cell for onsite power?
It depends on the system.
A solid oxide fuel cell (SOFC) is more efficient and cheaper to run, but costs far more to build and can't follow prices the way a genset does. We modelled a 100 MW UK data centre with a 50 MW grid connection, co-located solar and storage, and either a gas genset or an SOFC.
Gas genset
Cheaper to build and follows prices
SOFC
More efficient and cheaper to run
What matters most for your site?
Pick one to see which comes out ahead in our model.The SOFC. About 60% efficient against 40%, and £277m less to run over 20 years in our model.The gas genset. £1,000/kW to build against £5,000/kW for the SOFC.The gas genset. It ramps at 20% per minute against 1%, so it can chase price spikes and back off when solar is strong.
Electrical efficiency
Higher is better
Capex
Lower is better
Ramp rate
Higher is better
20-year opex
Lower is better
What the model showed
The SOFC cut 20-year opex by £277m but ran like a baseload asset; the genset ramped for price spikes and backed off when solar was strong.
What can you model for a data centre site?
The load and its connection, with battery storage, gensets and fuel cells, solar and wind, and flexible compute, on one site or as a microgrid.
Frequently asked questions
Can't see your question?
Get in touch →In Great Britain, yes for most arrangements. Since a 2023 rule change, active network management connections carry a contractual ceiling on annual curtailment hours, with compensation due beyond it. Technical Limits connections, where the congestion is on the transmission network, and Ireland's real-time curtailment arrangements carry no such ceiling and no compensation.
A phased connection lets capacity scale up over time in line with a data centre's build-out and ramp-up. Ofgem's February 2026 call for input on demand connections reported clear developer appetite for phased arrangements, and Ireland's flexible demand connections already convert to firm once reinforcement is complete.
Larger ones do. Under the CRU's December 2025 decision, they must build dispatchable generation or storage matching their contracted capacity, sell it into the wholesale market, and cover 80% of annual demand with new Irish renewables within six years. Meeting this brings exemption from emergency curtailment.
As of August 2026, Australia plans a national framework requiring large data centres to offset their demand. The AEMC's advice proposes certificate and firm-contract obligations, market registration and incentives to flex and co-locate. Behind-the-meter generation and storage would reduce the certificate obligation, and flexibility and storage would reduce the firming requirement.
Yes, for some non-critical workloads. In a five-day trial in December 2025 at Nebius's London data centre, Emerald AI, EPRI, National Grid, Nebius and NVIDIA cut power demand by up to 40% while critical workloads ran as normal. Batch inference and overnight processing are the likeliest loads to shift.
Yes. You can add generators of any fuel type with their operating parameters, including ramp rates, heat rate curves and must-run periods. Model them with a constrained grid connection, solar and battery storage, then compare scenarios on cost, emissions and unserved load in the GB electricity market and 40+ others.
Related pages
Request a live demo
See Gridcog on your own project.
Tell us a little about what you're modelling and we'll shape the demo around it. Bring your own price curves and assumptions, or use ours.
The team behind Gridcog

Fabian Le Gay Brereton
Chief Executive Officer & Co-Founder
Previously co-founded Greensense, acquired by ERM Power (now Shell Energy).

Pete Tickler
Chief Product Officer & Co-Founder
Co-founded Greensense and led digital innovation at ERM Power (now Shell Energy).

Genna Boyle
Chief Commercial Officer & Head of EMEA
More than 10 years in energy strategy, trading and renewables, with senior roles at Battery Optimiser and Limejump.